We’re ahead of schedule! Our contracted company, Central Cable, began plowing the main line on July 28. This phase of construction is expected to take approximately 3–4 weeks to complete.
Stop by and visit our staff at 204 S Main Street in Westfield, right next to the pharmacy!
Whether you have questions or are ready to sign up for services, our team is here to help!
Watch our Facebook page for weekly hours of operation.
Drops to each home or business who has completed a permission to bury form should be completed near the end of November.
Splicing is now complete in the Phase One area, bringing us one step closer to connecting homes.
The first group of homes that submitted a permission to bury along with an application were completed and connected by the end of January. As more homes became ready, they were quickly brought online.
Ready to get connected? Be the next home in your area by filling out an application for service to start the process.